The project.

A combined leisure brief

Working with Pulse Fitness for North East Derbyshire Borough Council, SPC was commissioned to project manage the new-build scheme in 2017. The brief brought swimming, fitness and sports facilities together within an accessible new centre.

Coordinating the scope

The project included a 25-metre pool, baby pool and slide, changing facilities, sauna and steam room. Dry facilities included a sports hall, spin and dance studios, gym, offices and welfare spaces, alongside landscaping, parking, cycle storage and an access road.

Delivery against programme and budget

The scheme took 14 months on site and was completed on time and within the £4 million budget.

LET’S TALK ABOUT YOUR NEXT PROJECT

What is next for your leisure facilities?

Tell us about the planned work and where your team needs support.

SPC Construct

For commercial construction, fit-out and refurbishment, speak to SPC Construct. SPC Partnership provides the consultancy; SPC Construct delivers the building work.

Visit SPC Construct